Fanellan power line diversion could face council objection

Highland Council planning experts recommend objecting to SSEN Transmission's plan to divert 1.7km of the Beauly to Denny line for the Fanellan substation, citing incomplete cumulative impact assessment.

Fanellan power line diversion could face council objection
Graphic: Amrit Khabar NewsroomImage rights policy

Key facts

Length of diversion
1.7km
Distance from Kiltarlity
2.4km
Distance from Beauly
4.5km
Maximum tower height
59.4m
Construction period
nine months (if seven days a week)
Final decision maker
Scottish Government

Background

SSEN Transmission has submitted plans to temporarily and then permanently divert 1.7km of the existing Beauly to Denny overhead line in Beauly. The diversion is intended to accommodate the proposed Fanellan substation, which has not yet been approved.

The Fanellan substation is currently undergoing a public enquiry following a previous council objection in February. The diversion is described as an 'essential' part of the proposed substation, yet it has not been included in the diversion's cumulative impact assessment.

Current situation

Highland Council planning experts have recommended that the south planning committee object to the diversion. They argue that the full cumulative impact of the application could not be assessed because the Fanellan substation was omitted from the assessment.

The south planning committee is due to meet on Thursday. The diverted overhead line would be located at Fanellan, 2.4km from Kiltarlity and 4.5km from Beauly. The council report notes that a 'significant local population' lives in small settlements within the area.

The diversion would replace the current 400kV/275kV line with a 400kV line and loop around the proposed substation. It would involve the removal of two existing towers and the installation of six new towers, with a maximum tower height of 59.4m. A temporary diversion would keep the network 'fully operational' during construction, which is estimated to last nine months if work takes place seven days a week.

Key figures for Fanellan power line diversion
Item Value
Length of diversion1.7km
Distance from Kiltarlity2.4km
Distance from Beauly4.5km
Maximum tower height59.4m
Construction periodnine months (if seven days a week)
All figures as stated in the source article.

Impacts

Kiltarlity Community Council has objected to the plans, arguing that a single environmental impact assessment should have been created for the whole project, including the substation. It says the project would have 'significant' impacts on landscape, natural heritage, and local communities during construction.

No public objections were received by Highland Council or the Energy Consensus Unit (ECU). However, the development is classed as a national one, so the final decision rests with the Scottish Government, regardless of any council objection.

Future outlook

Scenario analysis: The possibilities below are not certain predictions.

If the south planning committee objects this week, the objection will be forwarded to the Scottish Government, which will make the final decision on the diversion. The outcome of the Fanellan substation public enquiry may also influence the process.

Should the Scottish Government approve the diversion, construction could begin after the substation is approved, with a nine-month construction period if work proceeds seven days a week. If the substation is not approved, the necessity of the diversion may be reconsidered.

The council's concern about cumulative impact could lead to further assessments or modifications to the plans, potentially delaying the project. The final timeline remains unclear.

Source: inverness-courier.co.uk